ScheduleΒΆ

@startgantt

skinparam dpi 300

saturday are closed
sunday are closed
2025-02-17 to 2025-02-23 are closed
2025-04-14 to 2025-04-20 are closed

Project starts the 2025-02-03
projectscale weekly zoom 2
'title Project Integration

-- Deadlines --

[   EIE Practicals] as [eie] happens 2025-02-14
[   Project Plan] as [dplan] happens 2025-02-14
[   User Requirements] as [ureq] happens 2025-02-28
[   System Requirements] as [sreq] happens 2025-03-07
[   Functional Design] as [dfunc] happens 2025-03-21
[   PCB] as [dpcb] happens 2025-03-21
[   ACS Practicals] as [acs] happens 2025-03-28
[   Assessment Practicals] as [pract] happens 2025-04-04
[   Technical Design] as [dtech] happens 2025-04-11
[   Demo] as [demo] happens 2025-06-06

[ureq]  displays on same row as [eie]
[sreq]  displays on same row as [dplan]
[dfunc] displays on same row as [ureq]
[acs]   displays on same row as [sreq]
[pract] displays on same row as [dfunc]
[dtech] displays on same row as [acs]
[demo]  displays on same row as [pract]

-- Q3: Planning --

[Project plan] as [pplan] requires 2 weeks and ends at [dplan]'s end

[Gather user requirements] as [gureq] ends at [ureq]'s end
[pplan] -> [gureq]

then [Gather system requirements] as [gsreq] ends at [sreq]'s end

[Explore sensors] as [esen] requires 4 days
[Explore actuators] as [eact] requires 4 days
[pplan] -> [esen]
[pplan] -> [eact]

[Morphological analysis of hardware] as [hmor] requires 1 day
[esen] -> [hmor]
[eact] -> [hmor]

[PCB design] as [pcb] ends at [dpcb]'s end
[hmor] -> [pcb]

[Explore joints] as [ejoint] requires 1 week
[pplan] -> [ejoint]

[Morphological analysis of joints] as [jmor] requires 1 day
[hmor] -> [jmor]
[ejoint] -> [jmor]

[Mechanical design] as [dmech] ends at [dtech]'s end
[hmor] -> [dmech]
[jmor] -> [dmech]

[Order parts] as [parts] requires 1 day
[jmor] -> [parts]

[Receive parts] as [recv] requires 1 day
[recv] starts 2025-03-24
[recv] starts 14 days after [parts]'s end

[Test sensors using ESP32] as [tsen] requires 4 days
[Test actuators using ESP32] as [tact] requires 4 days
[recv] -> [tsen]
[recv] -> [tact]

[Explore control loops] as [eloop] requires 1 week
[pplan] -> [eloop]

[Control loop design] as [dloop] ends at [dtech]'s end
[hmor] -> [dloop]
[eloop] -> [dloop]

[Database design] as [ddb] requires 2 weeks
[eloop] -> [ddb]

[Webapp design] as [dweb] ends at [dtech]'s end
[ddb] -> [dweb]

-- Q4: Implementation --

[Construct the glove] as [const] requires 6 weeks
[dmech] -> [const]

[Implement control loop] as [iloop] requires 6 weeks
[dmech] -> [iloop]
[dloop] -> [iloop]
[tsen] -> [iloop]
[tact] -> [iloop]

[Setup database] as [idb] requires 1 week
[idb] starts 2025-04-21
[ddb] -> [idb]

[Implement webapp] as [iweb] requires 5 weeks
[dweb] -> [iweb]
[idb] -> [iweb]

[Prepare for the demo] as [pdemo] ends at [demo]'s end
[const] -> [pdemo]
[iloop] -> [pdemo]
[iweb] -> [pdemo]

@endgantt